Construction Contract Info

Contract Details

 Contract #1

Scope of Work:
The Environmental Mitigation contract has been divided into five parts as listed below.

Contract Prime Contractor
Amt.
Plant Collection, Salvaging and Propagation
Hanford $0.6M
Historic Building Stabilization Centric Construction $2.0M
Tree Program Professional Tree Care Co.
$3.0M
Advanced Geotechnical Work Malcolm Drilling $0.5M
Wetland Mitigation TBD $2.8M

Status:
Plant Collection, Salvaging and Propagation, Tree Program, Historic Building Stabilization, and Advanced Geotechnical Work contracts have been awarded and are in progress.

View a Fact Sheet for Contract #1 [70 KB pdf]

 Contract #2

Scope of Work:
Utility Relocation

Prime Contractor: Ghilotti Bros., Inc.
Contract Amount:   $19.0M

Status:
Contract has been awarded and work is in progress.

View a Fact Sheet for Contract #2 [1.72 MB pdf]
View the Utility Relocations Map [2.65 MB pdf]

 Contract #3

Scope of Work:
Permanent Roadway Section, Southbound High Viaduct, Southern Park Presidio Interchange, Ruckman Undercrossing

Prime Contractor: C.C. Meyers

Status:
Work is in progress. Construction began December 2009.

View a map of Contract #3 [3.8 MB pdf]

View plans as advertised

 Contract #4

Scope of Work:
At-Grade Detour, Southbound Battery Tunnel, Permanent Roadway Section, Electrical and Mechanical Substation, Retaining Walls, Traffic Switch

Prime Contractor: R&L Brosamar, Inc.

Status:
Work is in progress. Construction began in April 2010.

Click here for more details.
View a Fact Sheet for Contract #4 [465 KB pdf]
View a map of Contract #4
[3.8 MB pdf]

View plans as advertised

 Contracts #5-8 - Delivered Through Public-Private Partnership

Scope of Work:
Main Post Tunnels, Northbound Battery Tunnel, Northbound High Viaduct, Girard Road Interchange, Northern Park Presidio Interchange, Landscaping, Maintenance

Private Concessionaire: Golden Link Partners

Equity Member 1: HOCHTIEF AG 
 
Equity Member 2: Meridiam Infrastructure North America Fund II
 
Lead Engineering Firm: HNTB Corporation
 
Lead Contractors: Flatiron West, Inc., Kiewit Infrastructure West Co.  
 
Lead Operations and Maintenance: HOCHTIEF PPP Solutions North America, Inc.

Status:
Partnership agreement signed. Financial close expected in late summer 2011.

 

 